Assignment 3 – ECT/IS 372:
Microsoft Project II
|
Number |
Task
Description |
Duration(Days) |
Predecessors |
|
1 |
Develop
scope document |
5 |
None |
|
2 |
Develop
+/-100% business case |
3 |
None |
|
3 |
Provide
+/- 100% cost estimates |
2 |
None |
|
4 |
Validate
resource cap. & impact to delivery calendar |
2 |
1,2 and 3
must be complete |
|
5 |
Present
to SMT & gain approval |
2 |
4 must be
complete |
|
6 |
Engage
Impacted Organizations |
2 |
5 must be
complete |
|
7 |
Develop
high level business requirements |
5 |
5 must be
complete |
|
8 |
Present
to working group |
1 |
7 must be
complete |
|
9 |
Develop
high level tech approach |
3 |
8 must be
complete |
|
10 |
Facilitate
completion of +/- 50% business case |
2 |
8 must be
complete |
|
11 |
Develop
+/- 50% business case |
2 |
8 must be
complete |
|
12 |
Provide
scoping input for business case |
3 |
8 must be
complete |
|
13 |
Get business
LOB signoff |
1 |
7,8,9,10,11,12
must be complete |
|
14 |
Validate
resource cap. & impact to delivery calendar |
2 |
13 must
be complete |
|
15 |
Present
to SMT & gain approval |
1 |
13,14
must be complete |
|
16 |
Project Manager
assigned to project |
3 |
15 must
be complete |
|
17 |
Send
project approval communiqué |
1 |
15 must
be complete |
|
18 |
Engage
Corporate Infosec |
1 |
15 must
be complete |
|
19 |
Request
team resources |
1 |
15 must
be complete |
|
20 |
Commit
& provide resources for team |
3 |
19 must
be complete |
|
21 |
Build
high level project plan |
5 |
16,17, 18
& 20 must be complete |
|
22 |
Coordinate
project kickoff meeting |
2 |
15 must
be complete |
Note: You don’t have to put any durations in these at this point.